2020 Surface Treatment Project

Project Information

  • Project No.:  0672-6U2185          

Project Description:  The project consists of applying a Type II Slurry Seal treatment to streets in the El Sobrante area and a Micro-surface treatment to streets in Alamo and North Richmond areas. Work will also include surface preparation (edge grinding), tree trimming, striping and pavement marking removal, and placement of thermoplastic striping and pavement markings

  • General Location: El Sobrante, Alamo, North Richmond
  • Supervisory District:  1,2, & 4
  • Location: Map (PDF)
  • Contract Cost (Est.): $3,250,000    
  • Project Manager: Pete Warden      
  • Bid Due Date: May 5, 2020
  • Working Days: 45
  • Construction Date: Summer 2020
  • Funding Source: SB1 Gas Tax

SB1 Logo FUND

Outreach Program: The bidder shall make a “Good Faith Effort”, and document this effort, to obtain sub-bid participation by MBE’s, WBE’s, OBE’s, SBE’s and LBE’s in accordance with the project special provisions to be eligible for award.  Bidders that have not attended a pre bid meeting in the last 12 months should attend the County pre bid meeting noted in the Notice to Contractors.  The pre bid meeting will include an overview of the Outreach Program requirements and staff will be available to answer your questions.

Project Links