Alhambra Valley Road Realignment

Project Information

Project No.:  0662-6U4095             

Project Description:  The work to be done includes re-aligning Alhambra Valley Road, establishing a 28-foot wide paved roadway, a roadside ditch, grading and striping.

  • General Location: Alhambra Valley Road, 0.4 miles west of Bear Creek Road           
  • Supervisory District: 5        
  • Location:  Alhambra Valley Road
  • Contract Cost (Est.): $245,000
  • Project Manager: Mo Nasser               
  • Bid Due Date: TBD               
  • Funding Source: Gas Tax (SB1), Measure J Funding
  • Working Days: 30
  • Construction Date: Summer 2020

sb1-logo

Outreach Program: The bidder shall make a “Good Faith Effort”, and document this effort, to obtain sub-bid participation by MBE’s, WBE’s, OBE’s, SBE’s and LBE’s in accordance with the project special provisions to be eligible for award.  Bidders that have not attended a pre bid meeting in the last 12 months should attend the County pre bid meeting noted in the Notice to Contractors.  The pre bid meeting will include an overview of the Outreach Program requirements and staff will be available to answer your questions.

Project Links

  • Notice to Bidders
  • Planroom
    • PS&E package
    • Bidders List
    • Q&A
  • Bid Results (PDF)