Crockett Guardrail Upgrade

Project Information

  • Project No.: 0662-6R4105
  • Federal No.:  HSIP-5928(157)

Project Description:  The project will replace existing Metal Beam Guardrail (MBGR) system including posts, railing, and end treatments with Midwest Guardrail System (MGS). Guardrail will have both wood and steel posts. Work is to occur in the Crockett Area, along the following roadways; San Pablo Avenue, Cummings Skyway, Pomona Street, Carquinez Scenic Drive, and Crockett Boulevard.                                            

  • General Location: Various roads in the Crockett Area
  • Supervisory District: 5
  • Location: Crockett
  • Contractor: Coral Construction Company      
  • Project Engineer: Carlos Melendez, UNICO Engineering, Inc
  • Start Date: February 28, 2022
  • Working Days: 40
  • Estimated Completion Date: May 2022
  • Funding Source: Highway Safety Improvements Project Funding, and Local Gas Tax 