Mayhew Way and Cherry Lane Trail Crossing Enhancement Project

Project Information

Project No.:  0662-6R4137              

Project Description:  The work to be done generally consists of installing rectangular rapid flashing beacons at 2 sites: the Iron Horse Regional Trail crossing at Mayhew Way and the Contra Costa Canal Trail crossing at Cherry Lane in Walnut Creek. Work at the Mayhew Way site will also include construction of sidewalk bulb-outs on Mayhew Way, surface application of detectable warning surfaces on curb ramps, and tree trimming. Work at the Cherry Lane site will also include removal of existing in-ground flashers on Cherry Lane, surface application of detectable warning surfaces on curb ramps, and vegetation trimming.

  • General Location: Iron Horse Regional Trail crossing at Mayhew Way and Contra Costa Canal Trail crossing at Cherry Lane, Walnut Creek, CA
  • Supervisory District: 4
  • Location:  Location map (PDF) 
  • Contractor: Sposeto Engineering, Inc.
  • Resident Engineer: Paul Tehaney, Jon Suemnick
  • Start Date: TBD          
  • Funding Source: TDA, Gas Tax
  • Working Days: 30  
  • Est Construction Date: TBD

Project Links

Outreach Program: The bidder shall make a “Good Faith Effort”, and document this effort, to obtain sub-bid participation by MBE’s, WBE’s, OBE’s, SBE’s and LBE’s in accordance with the project special provisions to be eligible for award.  Bidders that have not attended a pre bid meeting in the last 12 months should attend the County pre bid meeting noted in the Notice to Contractors.  The pre bid meeting will include an overview of the Outreach Program requirements and staff will be available to answer your questions.