RProject No.: 0662-6R4139
State Project No.: HSIPSL-5928(162)
Project Overview
Work generally consists of updating signal hardware including installing Advanced Dilemma Detection Zone systems, improve pedestrian crossing signal hardware, installing LED signal lights, and retroreflective backplates at 9 intersections on San Pablo Dam Road between El Portal Drive and Castro Ranch Road and 2 intersections on Bailey Road from Willow Pass to Canal Road.
Project Location
San Pablo Dam Road (PDF) in El Sobrante between El Portal Drive and Castro Ranch Road
Bailey Road (PDF) in Bay Point between Willow Pass Road and Canal Road
Supervisory District: I and V
Project Funding
HSIPSL State Funds
Local Road Funds
Contract Cost Estimate: $917,000
Project Schedule
Advertise Date: June 6, 2023
Bid Due Date: July 18, 2023
Estimated Start of Construction: October 2023
Estimated Completion Date: Winter 2023
Contact Information
Project Manager: Randolf Sanders
Email: [email protected]
Contractor: DC Electric Group, Inc.
Outreach Program
The bidder shall make a “Good Faith Effort”, and document this effort, to obtain sub-bid participation by MBE’s, WBE’s, OBE’s, SBE’s and LBE’s in accordance with the project special provisions to be eligible for award. Bidders that have not attended a pre bid meeting in the last 12 months should attend the County pre bid meeting noted in the Notice to Contractors. The pre bid meeting will include an overview of the Outreach Program requirements and staff will be available to answer your questions.