Posted on: July 30, 2020

[ARCHIVED] Second Phase of Countywide Guardrail Upgrade to start in Clayton

Contra Costa County Public Works 

to Continue Construction on the Countywide Guardrail Upgrade Project

 

July 30, 2020, Clayton, CA – The Contra Costa County Public Works Department will begin the second phase of construction on the Countywide Guardrail Upgrade Project on Marsh Creek Road. Guardrail work is scheduled for the following locations:

Vasco Road: Construction began on Wednesday, July 15, 2020 and is anticipated to be completed by Friday, August 7, 2020. The work will occur Monday through Friday, 6:00 pm to 6:00 am, barring unforeseen circumstances. Work will take place between Walnut Boulevard and the Alameda County Line.

Marsh Creek Road: Construction is expected to begin on Monday, August 3, 2020. The work will occur Monday through Friday, 8:00 am to 3:00 pm, barring unforeseen circumstances. Work will take place between the Clayton City limit and Camino Diablo.

San Pablo Dam Road: Construction is expected to begin in late-August, 2020. The work will occur Monday through Friday, 8:00 am to 3:00 pm. Work will take place between the Richmond City limit and Bear Creek Road.

Construction will be complete in mid-September 2020, barring unforeseen circumstances. Construction operations will be scheduled to minimize impacts to commute traffic. Drivers can expect delays up to 15 minutes during construction. Current social distancing protocol will be observed.

This project is funded by the Highway Safety Improvement Program (HSIP), East County Area of Benefit, and gas tax funds.  More information for this project can be found at http://www.cccounty.us/pwdmap.

Countywide Guardrail Upgrade Project  Work Areas 7 2 2020

 

Contact: Construction Status: Paul Tehaney, (925) 595-6012; Project Status: Dante Morabe, (925) 726-6901

####